O/O Chief Engineer/NCES Chennai-2
Circular Memo NO.CE/NCES/SE/EE/WPP/AEE2/F.TNERC Order No.3 dt. 15.05.06 D.1076/2007 dated 19.10.2007
Sub: Elecy. - NCES – Releasing of payment of Wind Power Purchase at the rate of Rs.2.90/- per unit for the WEGs commissioned on (or) after 15.05.06 – instruction issued –reg.
Ref: 1. TNERC Order No.3 dated 15.5.2006 2. Circular Memo No.CE/NCES/SE/EE/WPP/AEE2/F.TNERC order/ D.652/07 3. Circular Memo No.CE/NCES/SE/EE/WPP/AEE2/F.TNERC/ D.843/ 07 dt. 14.09.07 ******* The Tamil Nadu Electricity Regulatory Commission (TNERC) Order No. 3 dt. 15.3.2006 was implemented in Circular Memo vide reference(2) and the working instructions was already issued vide reference (3) for implementing the TNERC order No.3 dt. 15.05.06 for the NCES based generating plants.
Representations have been received that the purchase price fo Rs.2.90/- per unit has not been adopted to the developers who have commissioned the WEG’s on (or) after 15.05.06 due to non execution of EPA/EWA.
Based on the various representation received from wind mill developers regarding the wind energy power purchase rate, it is hereby instructed to pay at thep rate of Rs.2.90/- per unit and also to release the difference in the unit rate (Rs.2.90/- - Rs.2.70/-) only for the WEGs commissioned on (or) after 15.05.06, pending execution of EPA and EWA.
Receipt of this circular memo may be acknowledged.
(BY ORDER OF THE CHAIRMAN)
Sd/- (C. SANTHANA GOPALAKRISHNAN) CHIEF ENGINEER/NCES For CHAIRMAN/TNEB ToAll Superintending Engineers of Electricity Distribution Regions. The Superintending Engineer / WEDC /Udumalpet and Tirunelveli.
Copy to: All Chief Engineers / Distribution Regions Chief Financial Controller/ General/Chennai-2 Chief Engineer/ Commercial/Chennai-2 Chief Engineer/Planning/Chennai-2 The Executive Director/Operation/Chennai-2 The Chief Internal Audit Officer/Chennai-2 The Director/Tariff Cell/Chennai-2
|