|
AGREEMENT BETWEEN
AND TAMIL NADU ELECTRICITY BOARD FOR THE PARALLEL OPERATION AND SALE OF
SURPLUS POWER FROM
CO-GENERATION PLANT BY TENB.
THIS AGREEMENT entered in to at
. on the
day of
., Two thousand
four Between a company incorporated under the companies Act, 1956 (CA1
of 1956) having its registered office at
. (hereinafter called the
SUGAR MILL / POWER GENERATING COMPANY) represented by Thiru.
.,
as party of the FIRST PARK and the Tamil Nadu Electricity Board, a body
corporate constituted under the Electricity (Supply) Act, 1948 (C.A.54
of 1948) having its office at N.P.K.R.R. Maaligai, Electricity Avenue,
800, Anna Salai, Chennai-2, represented by Thiru
Superintending Engineer /
. EDC (hereinafter called the
Board) as party of the SECOND PART.
WHEREAS the Sugar Mill / Power generating
company has informed the Board of its intention to establish
.. MW
Co-generating power plant at
.. village,
.. Taluk,
. District to generate Electricity and to sell surplus power
applicable after its consumption.
AND WHEREAS the sugar mill / power
generating company has offered to sell the surplus power generated by
the Bagasse based Co-generating plant to the BOARD.
AND WHEREAS the BOARD has taken note of
the information about establishment of the said plant and has agreed to
purchase the surplus power on the terms and conditions hereinafter agree
to
NOW THESE PRESENTS
WITNESSETH and the parties hereto agree as follows :
-
The Sugar Mill / Power generating
company shall feed the surplus power from their bagasse based
co-generating plant into the Boards grid and the Board shall draw
the power and pay therefor.
-
There shall be direct transfer of power
from the plant to the grid of Tamilnadu Electricity Board and for
this purpose the generators of the Sugar Mill / power generation
company shall be permitted to be paralleled with the Boards Grid
subject to the terms and conditions imposed by the Board from time
to time.
-
The generating company shall be bound by
all the provisions of the Electricity Act 2003, statutory amendments
made form time to time and the directions of the Board issued from
time to time.
-
-
The Sugar Mill / Power generating
company shall be responsible for designing the generating set and
protection system of the plant for the safe parallel operation with
the Boards grid.
-
The company shall provide an exclusive
circuit breaker of the appropriate voltage level and rating at the
co-generation plant end for interconnecting the plant with TNEB
grid.
-
The company shall make good the losses,
if any, due to any damage that may be caused to the equipment /
lines of the Board resulting on account of parallel operation of its
plant.
-
The company
agrees that the Board will not be responsible for any damage to its
power plant resulting from parallel operation with the grid and that
the Board shall not be held liable to pay any compensation for any
such damage.
-
The
interfacing with the Boards grid shall be at the voltage level of
kV.
-
-
The Sugar mill / Power generating
companys annual maintenance requirements shall be from
..
to
. The Sugar mill / Power generating company shall inform
the Board of any changes in the maintenance schedule at least one
week in advance.
-
In the last week of every calender
month, the Sugar mill / Power generating company shall furnish to
the Board a supply plan indicating the quantum of energy likely to
be delivered during the next calender month. Arrangements shall be
made for transmission of on Line data of the generated power to Load
Despatch Centre. The anticipated generation for each day shall be
furnished one day in advance regularly.
-
The generating company shall obtain
prior permission of the Chief Engineer / Distribution concerned for
the drawal of start up power from the grid giving complete split up
details of preferential loads of the co-generation plant.
The power has to be availed through the interfacing line itself as
per provisions in permanent B.P. (CH) No.: 319, dt. 30.10.95 and
the amendments made from time to time.
-
The sugar mill / power company are
exempted from merit order backing down as per (Per) B.P. (FB) No :
42 (TB) dt. 24.4.02.
-
Billing and payment : The Sugar mill /
power generating company shall prepare bill every month based on the
meter reading certified by the TNEB / in accordance with the
provisions of the PPA in duplicate and forward it to the
Superintending Engineer concerned for scrutiny and counter signature
/ certification. The bill so presented will be settled by TNEB in a
reasonable time either to the Sugar mill / power generating company
or to the person authorized by them at its discretion with the
prior, approval of TNEB, by way of crossed cheque payable at
Chennai. Board is entitled to recover any excess payment or any
other dues to TNEB from the sugar mill / power generator in
subsequent bills.
-
-
The Sugar mill / Power generating
company agrees that the purchase price of bagasse based energy
generated and exported during the crushing season, between 1st
December and 30th June of the suceeding year, shall be
paid at the rates specified in para 4 (i) of the permanent B.P. (FB)
No : 1 dt. 11.1.2000 and as amended from time to time.
-
The purchase price of energy generated
and exported during seasonal period between 1st December
and 30th June of the succeeding year by using
conventional fuel in the boiler shall be paid at the rate specified
in B.P. (FB) No : 93 Technical branch dated 16.5.2000 and as
amended from time to time.
-
The purchase price of the energy
generated and exported during off-seasonal period between 1st
July and 30th November by using conventional /
non-conventional fuel in the boiler shall be at the rate specified
in B.P. (FB) No. 93 (TB) dt. 16.5.2000 and B.P. (FB) No : 92
dt.7.7.2001 and as amended from time to time.
-
The Sugar mill / power generating
company agrees that a 2% deduction from the total energy exported
shall be made towards line losses.
-
-
The Sugar mill / Power generating
company is permitted to wheel the bagasse based power to its
subsidiary company situated with in a radius of 25 km from the
Sugar mill / Power generating company / Co-generation plant after
deducting 2 % of the energy exported as wheeling charges. Wheeling
beyond 25 kms of radius to anywhere in the State is also permitted
after deducting 10% of the energy exported as wheeling charges
during the seasonal period and 1 5% of the energy exported during
the off-seasonal period. Wheeling of energy is restricted to a
maximum of 2 Nos. H.T. Industrial Tariff - I, Service connections
coming under the same distribution circle only.
-
A certificate from the Superintending
Engineer of the Electricity Distribution Circle concerned shall be
obtained for the energy wheeled to the own or subsidiary company and
enclosed with the monthly bill.
-
Metering arrangements shall be provided
at the Sugar mill / Co-generation plant premises at the companys
cost for measuring import and export of power with maximum demand.
-
-
(i) Drawal of power from Boards grid
as recorded by the import meter shall be charged at Boards
H.T.Tariff I rate applicable for Industrial consumers. Maximum
Demand charges shall be charged as notified by the TNERC from time
to time. Penal and other surcharges shall be levied as per the
notified tariff conditions if the sanctioned demand is exceeded or
power is availed during peak load hours as the case may be or as per
conditions imposed from time to time by the Board & TNERC.(ii)
Power drawn from the TNEB grid for the purpose of Sugar mill /
Co-generation plant for maintenance works, trail run of equipments,
water works etc., shall be charged under Boards H.T. Tariff III
including M.D. charges as notified by the TNERC from time to time.
-
The average power factor during the
billing period for the power drawn from TNEB grid is to be
maintained betweeen 0.9 lag and unity. Penalty shall be imposed at
the rates stipulated in the notified tariff for the low power factor
less than 0.9 lag.
-
The Sugar mill / Power generating
company shall install a static main meter and a check meter in the
Sugar Mill / Power generating company at its cost to record the
power supplied by the Sugar Mill / Power generating company to the
Board. The static meter should record both export and import
separately.
-
The meters shall be jointly inspected,
calibrated and sealed on behalf of both the parties and shall not be
interfered with by either party except in the presence of other
party or its representatives.
-
The main meter and the check meter shall
be test checked for accuracy once in six months and shall also be
calibrated and adjusted by Meter Relay Test wing of the Board once
in a year.
-
The meters
shall be deemed to be working satisfactorily if the errors as
determined in the test are within the limits specified in the
relevant specification applicable to high precision energy meters.
-
The consumption registered by the main
meter alone shall be taken for the purpose of billing as long as the
error in the main meter is within the permissible limits specified.
-
If, during the half yearly test check or
annual calibration, the main meter is found to have errors within
permissible limits, the billing shall be done as per the main meter.
If the check meter is found to have error beyond permissible limits,
the check meter shall be calibrated.
-
If, during the half yearly test check or
annual calibration, the main meter is found to have errors beyond
permissible limits, but the check meter is found to have errors
within the permissible limits the billing for the previous 3 (three)
months shall be revised based on the consumption recorded by the
check meter. The main meter shall be calibrated immediately and the
billing thereafter shall be as per the main meter.
-
If during the half yearly test check or
annual calibration, both the main meter and the check meter are
found to have errors beyond permissible limits, the bill shall be
revised for the previous 3 (Three) months by applying correction as
determined by the MRT / Wing of the Board to the consumption
registered by the main meter.
-
If both the main meter and the check
meter fail to record energy either due to the blowing of the P.T.
fuses or due to any other causes, the energy exported during the
period of outage will be computed as in Clause (i) above.
-
All the testes on the main and check
meters shall be conducted by the Meter & Relay Test (MRT) laboratory
of the Board in the presence of the representative of company and
the results / correctness so arrived at shall be applicable and
binding on both the parties and the same cannot be subject to any
dispute.
-
Settlement of disputes Arbitration
If any dispute or difference of any kind
what soever arises between the parties relating to this agreement, it
shall in the first instance be settled amicably with intervention of the
Chief Engineer Non Conventional Energy Sources of the Board within sixty
(60) days, failing which the matter shall be referred to a sole
arbitrator as nominated by the Chairman of the Board. If the matter is
so referred to the Sole Arbitrator for arbitration, the arbitration
shall be conducted by the arbitrator in accordance with the provisions
of arbitration and conciliation Act, 1996 or any other enactment or
statutory modifications thereof for the time being in force. Decision of
the sole Arbitrator in this regard shall be final and binding upon the
parties.
-
The Sugar mill / power generating
company is entitled to bank the energy generated as per orders that
are in force issued by the Board and as amended from time to time.
-
The Sugar mill / power generating
company agrees that the Board shall have the right to vary from time
to time, the tariff, policy on banking and wheeling and terms and
conditions of this agreement by special or general proceedings and
the conditions relating to generation of electricity through
Co-generation and such other variations ordered by the TNERC and
TNEB shall be binding on the company.
-
The Board reserves the right to
terminate the agreement if any of the conditions laid down by the
TNEB / CEIG / TNERC is not complied with by the power generating
company of for any other reasons.
-
Duration
The agreement shall remain in force, for a
period of 15 (fifteen) years or for the useful life period of the plant,
whichever is less, from the date of this agreement.
In case the Board continues to get power
from the power generation plant, after the expiry of this agreement,
without renewal or formal extension thereof, then the provisions of the
agreement shall be continued to be operative till the agreement is
formally renewed, extended or replaced within one year from the date of
expiry. Then for the purpose of billing and payment in respect of the
supply of energy received from the power generating company during such
period, the rate applicable for, as on the date of expiry of the
agreement shall be adopted. It shall however be the endeavor of the
power generating company and the Board to finalize the next agreement
before the expiry of the agreement.
-
Implementation of the agreement
-
All discretions to be exercised and
direction, approvals, consents and notices to be given and actions
to be taken under these presents, unless otherwise expressly
provided herein, shall be exercised and given by the signatories to
this agreement or by the authorised representatives (s) of that
party, nominated in this behalf and notified in writing to the other
party.
-
All notices with regard to default or
difference relating to this agreement shall be in writing and signed
by the signatories to this agreement or by the authorized
representative(s). Each such notice shall be deemed to have been
duly given or sent by the party concerned, if the notice is
delivered against acknowledgement due to the signatories or the
authorised representative(s) at their respective address.
-
The parties shall ensure compliance of
the terms of this agreement.
The expressions Sugar mill / power
generating company and The Board herein before used shall include
their respective successors and assigns in office. IN WITNESS WHERE OF
Thiru
for and behalf of the Sugar mill / Power
generating company and Thiru.
..
for and on
behalf of the Board have hereunto set their signatures on the day,
month and year first above mentioned.
SIGNATURE
In the presence of Witnesses :
1.
2.
SIGNATURE
In the presence of Witnesses :
1.
2.
|